Slno |
Name of work |
Nature of work |
Year |
Value ( Cr ) |
Client |
Project |
Remark |
1 |
Road work,Surge Salt, T.R.T(PORTAL), |
Excavation of Rock & Culverts , Causeway Well, Concrete Wall ,Supporting Work, Earth work |
2000-02 |
16.71 |
H.C.C |
D.G.H.E.P (Dharchula) |
Completed |
2 |
Head Race Tunnel |
Underground Excavation,Lining Concrete Work & Supporting Work |
2001-06 |
25.78 |
Samsung |
D.G.H.E.P (Dharchula) |
Completed |
3 |
Mining & Transporting Boulders |
Mining & Transporting, Benching (Haul Road) & Related Activities |
2003-06 |
8.92 |
Gamuda |
NH-2 Pachami (W.B) |
Completed |
4 |
Mining & Transporting Boulders |
Mining & Transporting, Benching (Haul Road) & Related Activities |
2006-07 |
10.05 |
Shristi |
NH-25 (UP-05 ) Four Lane |
Completed |
5 |
Supply of Boulders |
Mining & Transporting, |
2006-10 |
51.00 |
IRCON |
NH-25 (UP-05 ) Four Lane |
Completed |
6 |
Crusher Running & Maintenance |
Operation and Maintenance |
2007-10 |
8.78 |
IRCON |
NH-25 (UP-05 ) Four Lane |
Completed |
7 |
Mining & Transporting Boulders |
Mining & Transporting, Benching (Haul Road) & Related Activities |
2006-10 |
19.75 |
NCCL |
NH-25 (UP-05 ) Four Lane |
Completed |
8 |
Supply of Boulders |
Mining & Transporting, Benching (Haul Road) & Related Activities |
2009-10 |
1.45 |
K.M.C. |
NH-25 (UP-03 ) Four Lane |
Completed |
9 |
Supply of Aggregate |
Mining & Transporting, Crusher Running & Maintenance |
2008-09 |
11.81 |
GAYATRI |
NH-25 (UP-04) Four Lane |
Completed |
10 |
Fabrication & Erection |
Fabrication & Erection Of plate works & ESP Erection |
2010 |
2.83 |
Flsmith Pvt. Ltd. |
Utkal (Odisha) |
Completed |
11 |
Removal of Over burden & Supply of Boulders |
Mining & Transporting, Benching (Haul Road) & Related Activities |
2011-12 |
25.00 |
KSSIPL |
NH-203 Four Lane |
Completed |
12 |
BPTRP Earth Work Section-1 (Bhubaneshwar) |
Earth work Embankment, Subgrading. |
2011-12 |
13.00 |
KSSIPL |
NH-203 Four Lane |
Completed |
13 |
BPTRP Earth Work Section- 1 (Chandanpur) |
Earth work Embankment, Subgrading. |
2011-12 |
10.33 |
KSSIPL |
NH-203 Four Lane |
Completed |
14 |
Supply of Boulders |
Mining & Transporting, |
2011-12 |
11.00 |
GVR |
Dumka-Barhet Section, Jharkhand |
Completed |
15 |
Fabrication, Erection & Roofing works |
Fabrication, Erection & Roofing works at Cement Stores |
2012-13 |
0.61 |
ISOLUX |
Kudra, Aurangabad, Bihar |
Completed |
16 |
Earth Work |
Ash Dyke |
2013-14 |
6.00 |
KSS Petrol Pvt.Ltd |
Talwandi Sabo Power Project |
Completed |
|
|
|
|
|
|
|
|